November 2, 2007,
The sod for Honor Roll park has been delivered and laid.
Watering has begun of the recently laid sod to help it take hold. |
|
November 1, 2007,
The plant beds behind the monument surrounding the flag poles have been completed.
Plants have been added as well as additional plants have been added in various beds. |
|
October 31, 2007,
The walkway lights leading to Main Street have been installed
The lights to illumanate the flags have been installed. The area has been back filled.
Additional plants have been installed along the walkway to Main Street.
A few night shot to show the overall lighting setup at the monument. |
|
October 30, 2007,
The walkway leading to Meridian Road has had a brick border installed
Brick borders for the planting beds on the Northern side of the walkways has also been installed.
A few night shots to show the courtyard lights. |
|
October 29, 2007, Afternoon Updated
Mulch and plants have been added to the walkway leading to Main Street.
The site has been graded in preparation for future landscaping. |
|
October 29, 2007,
The forms for the sidewalk along Main Street around to Meridian Road have been constructed.
The four benches have been installed in between the granite service markers.
The brick border around the north west side of the monument has been installed. |
|
October 26, 2007,
The walkway leading to Meridian Road has had a brick border installed
Brick borders for the planting beds on the Northern side of the walkways has also been installed. |
|
October 25, 2007, Afternoon Updated
Mulch and plants have been added to the walkway leading to Main Street.
The site has been graded in preparation for future landscaping. |
|
October 25, 2007,
The ring of bricks for a border around the courtyard has been installed.
Mulch, plants, and the lights for the granite markers have been installed.
The brick border for the walkway leading to Main Street and been installed.
The soil for the center base area around the Fallen Soldier Sculpture has been added and leveled. |
|
October 23, 2007,
The walkway to Main Street has been completed.
The walkway paver bricks continue to be installed to Meridian Road. |
|
October 22, 2007,
The black markers representing each of the branches of service were installed.
The walkway pavers continue to be installed.
The pedestal base for the Fallen Soldier Sculpture has been installed.
The last image is a composite of the outer seals located on each marker. |
|
October 19, 2007,
The paver bricks continue to be installed.
The courtyard area has been filled. The walkway pavers are being installed.
The concrete has been poured for an extension for the bench to be placed. |
|
October 18, 2007,
The paver bricks continue to be installed.
John Mathews (gray shirt) and Bill Foote (red shirt) continue to install the engraved pavers in the courtyard. |
|
October 17, 2007,
The paver bricks have begun to be installed.
John Mathews (gray pullover) and Bill Foote (denim jacket) placing the engraved pavers in the courtyard. |
|
October 16, 2007, Afternoon Update
The Fallen Soldier Sculpture outer ring base has been back-filled.
The bases for the lights to surround the courtyard have been set. |
|
October 16, 2007,
Conduit for the lights and their base was installed.
The forms for the Fallen Soldier Sculpture base were removed. |
|
October 12, 2007, Afternoon Update
The concrete setting as is was just poured earlier this day for the walkways and courtyard slab. |
|
October 12, 2007,
The forms for the walkway to Main Street and Meridian Road were constructed. The concrete slab for the courtyard paver bricks was poured. The walkways to Meridian Road and Main Street were poured. Third picture shows Ready-Mix Service, Inc. pouring concrete with assistance of Dan Frey, Scott Pingel, and Larry Harris of Jamie Wilkenson, Inc. Fourth picture shows Dan Frey working on the walkway to Meridian Road. |
|
October 10/11, 2007,
The concrete ring for the Fallen Soldier Sculpture has been poured and the forms removed. The concrete slab for the paver brick wings has been poured and the formed removed. The wrought iron panels have been re-installed after they were refinished. |
|
October 9, 2007,
The concrete has been poured around courtyard circle. The Granite Markers will be set on the five light gray areas and the benches will be placed in between along this ring. |
|
October 8, 2007,
The three parking spaces along Meridian Road have been marked off and the walk way to the monument has been striped.
The gravel bedding has been spread out and construction of the forms for the pouring the concrete around the courtyard area has been completed. |
|
October 5, 2007,
Construction of the bases for the Granite Markers and Fallen Soldier Sculpture has been completed.
First picture shows Larry Harris, Scott Pingel, Jamie Wilkinson, Tom Sedlacek, and Will Shashack at Monument site during the construction of the Fallen Soldier Sculpture base.
The wrought iron panels which supported the pillars and plaques have been removed for restoration. Last image shows John Farmer removing the old hardware that held the panels in place. |
|
October 4, 2007,
The Monument site has been marked-off with the form layouts.
The courtyard area has been marked off to show the placement of the five granite markers surrounding the Fallen Soldier sculpture.
|
|
September 28, 2007,
The three parking spaces along Meridian Road have been poured and the asphalt set. |
|
September 25, 2007,
The sidewalk along Meridian Road from Main Street to the Bike Path has been poured. |
|
September 19, 2007,
The curb for the parking spaces has been completed.
The forms were set for the sidewalk and curbs along Meridian Road.
And the new curb along Main Street has been completed. |
|
September 12, 2007, The aggregate base was spread out after dirt for the three parking spaces was excavated.
A storm drain was installed and the trench was dug for water drainage. |
|
September 7, 2007, The monument site has been graded with the dirt that was delivered earlier this week. |
|
September 4, 2007, Backfill dirt has been delivered to the site for grading. |
|
August 29, 2007 The electrical meter was installed and underground electrical wires were ran from the pole to the meter base. The power pole/light pole for the flags was removed from the corner near the intersection. |
|
August 20, 2007,
The benches, sidewalks, and landscaping plants were removed. The conduit was connected to the meter box. |
|
August 13, 2007 Electrical meter box was installed for supplying electrical needs for the flags, courtyard, and future events. |
|
July, 2007 The Eagle and Orbs atop of the brick columns were re-finished. |
|
May 23, 2007 The three new flag poles were installed behind the monument.
The Restoration begins. |
|
November 2006 VFW Post 2222 Commander Ron Hicks addressing the crowd gathered during the annual March to The Honor Roll. |
|
circa 1947 An early picture of June Sedlacek and Ralph Weiler in front of The Honor Roll. |
|
circa 1943
Fanny, Carol, and Belle Rasplica stand in front of the 182 names carved into the recently completed Honor Roll. |
 |